Delivery and erection of CS, SS and ES piping at the Norske Skog plant


complete assembly of BFB boiler with HP and LP piping incl insulation


Assembly of 2 pcs of electrostatic precipitators 400 tons at the Smurfit Kappa plant


Retrofit of ESP in Billerud Korsnäs Plant in Gävle


Assembly and insulation of 1 ESP and ducts, scope of 310 tons in Boliden Rönnskär, Skellefteå


Assembly of boiler, piping, equipment, air and flue gas ducts - 2.100 tons