Order by Date Ascending Order by Date Descending | Order by Country Ascending Order by Country Descending

Sweden

Södra Cell / Värobacka
2002
Erection of 2 pcs of electrofilters (ESP) - 800 t - Södra Cell / Värobacka - 2001/02.




Svappavaara
2013
Assembly (part dismantling), insulation and electrical works of 3 x ESP, ducts and equipment - 1475 ton / 8296 m2




Sysav / Malmö
2002
Erection and insulation of 1 pc of electrofilter (ESP) - 300 t




Handelö / Norrköping
2002
Manufacturing, erection and insulation of bag filter - 160/250 t - Handelö / Norrköping-2001/02.




Jämtkraft / Östersund
2002
Erection and insulation of 1 pc of electrofilter (ESP) - 170t




Iggesund
2012

Assembly and insulation of 2 pcs of ESP and ducts – 820 ton





Handelö / Norrköping
2002
Erection of ducts, hoppers, ECO, 800 t - Handelö / Norrköping - 2001/02.




SAKAB/Kumla
2002
Manufacturing, erection and insulation of bag filter - 113/160 t - SAKAB/Kumla-2002.




Kiruna
2002
Dismantling, erection and insulation of electrofilter (ESP) - 80/48/450 t - LKAB Kiruna 2002.




Stockholm
2002
Modification of ESP installation - FORTUM Högdalenverket/Stockholm 2002.




Hässleholm Energi
2003
Manufacturing, erection and insulation of bag filter + 45/70 t - Hässleholm Energi 2002/03 2002.




Lilla Edet / SCA
2003
Erection of ducts - 49t - SCA / Lilla Edet 2003.




Solna / Norrenergi
2003
Manufacturing, erection and insulation of bag filter + 250/260 t - Norrenergi / Solna 2003




Borlänge / Stora Enso
2004
Assembly of bio fuel boiler 1700t - Stora Enso / Börlange 2003/04.




Borlänge / Stora Enso
2004
Erection and insulation of electrofilter (ESP) - 240 t + Stora Enso / Borlänge 2004




Sollefteå / Graninge
2004
Erection and insulation of electrofilter (type ELPAC 2) - 20 t - Graninge / Sollefteå 2004




Skoghall / Stora Enso
2004
Assembly of steel construction, ducts, installation - 1000 t - Stora Enso / Skoghall 2003/04




Skoghall / Stora Enso
2005
Assembly and insulation of 2 ESP - 526 ton - Stora Enso / Skoghall 2004/05




Skoghall / Stora Enso
2005
Welding of the boiler - Stora Enso / Skoghall 2004/05




Skoghall / Stora Enso
2005
Assembly of evaporation piping - Stora Enso / Skoghall 2004/05




Malmberget / LKAB
2006
Assembly of 3 ESP, 1 bag filter, ducts, tanks and gas suspension absorber - 1600 ton - LKAB Malmberget 2005/06




Piteå / Kappa Kraftliner
2006
Assembly of the boiler type Hybex, incl. piping, equipment, ducts, tanks – 1740 ton - Kappa Kraftliner – Piteå 2006




SCA / Obbola n.Umeå
2007
Assembly and insulation of 2 ESP and ducts – 375 ton




Ovik Energi / Ornskoldsvik
2008
Assembly of the boiler type Hybex, incl. piping, equipment, ducts, tanks – 1850 ton




Ovik Energi / Ornskoldsvik
2008
Assembly and insulation of 1 ESP and ducts – 235 ton  




Kalmar
2009
Assembly of the boiler type Hybex, incl. piping, equipment, ducts, tanks – 1608 ton




Mölndal
2009
Erection and insulation of bag filter, 150 ton.




Västerås
2014
Assembly of boiler, piping, ducts, equipment - 3000 ton




Karlstad
2014
Bag filter assembly and insulation, 102 ton / 1215 m2




Vimmerby
2014
Boiler assembly, delivery and assembly of piping - 205 ton / 40 ton




Linköping
2015
Erection (400 ton) and insulation (2.050 m2) of bag filter




NYBRO
2015
Erection of the boiler 265 ton, delivery/erection of piping 15 ton, delivery/erection of ducts and other steel construction 50 ton, insulation works 1.500 m2




Skövde
2015
Assembly of the boiler 233 ton, delivery and erection of piping 10 ton, erection of equipment 35 ton




Mönsterås
2017
Prefabrication, delivery and erection of evaporation plant, replacing of tanks, assembly of staircase in Södra Cell pulp and paper mill



Örebro
2017
Delivery and erection of steel construction for modernized boiler



Uppsala
2017
Erection, insulation and electrical works on new bag filter, 275 t construction, 2900 m2 insulation



Grums
2018
Prefabrication, delivery and erection of evaporation plant, replacing of tanks, assembly of construction in BillerudKorsnäs pulp and paper mill




Borås
2018
Assembly of boiler, piping, equipment, air and flue gas ducts - 2.100 tons



Skelleftehamn
2007
Assembly and insulation of 1 ESP and ducts, scope of 310 tons in Boliden Rönnskär, Skellefteå



Gävle
2017
Retrofit of ESP in Billerud Korsnäs Plant in Gävle



Lidköping
2021
complete assembly of BFB boiler with HP and LP piping incl insulation

Latvia

Launkalne
2012

Erection of boiler, prefabrication and erection of piping - 230 ton



Finland

Espoo
2013
Assembly of fabric filter type ELPAC




Valkeakoski
2005
Assembly and insulation of 1 electrostatic precipitator ESP with ducts 120 ton UPM Kymmene Valkeakoski 2005




Oulu / Stora Enso
2006
Assembly of 1 ESP with ducts – 470 ton - Stora Enso Oulu 2006




Vantaa
2013
Boiler erection, delivery and assembly of piping




Lohja
2015
Assembly of the boiler, piping, ducts, equipment and bag filter, totally 1.100 ton




Riihimäki
2016
Dismantling an old ESP, erection, insulation and electrical works of new ESP




Helsinki
2017
Prefabrication, delivery and erection of high and low pressure piping, air and flue gas ducts to the project Salmisaari

Denmark

Asneasverket
2004
Delivery, erection, insulation of SCR, ducts, piping (in consortium) - 900/1550 t - Asneasverket 2003/04




Aalborg / Reno Nord
2004
Erection and insulation of electrofilter (ESP) - 172 ton Reno Nord / Aalborg 2004


Germany

Arneburg / Zellstoff Stendal
2003
Erection of 3 electofilters (ESP) and ducts (in consoritum) 1110 t - Zellstoff Stendal / Arneburg 2003


France

Biganos
2009
Erection of bolier 622 ton, Ducts and equipment 641 ton, Piping 93 ton Bag filters 194 ton, Fuel and coarse equipment 157 ton.




Epinal
2014
Erection of the boiler and bag filter, delivery and erection of HP / LP piping


Norway

Hamar
2010
Erection and insulation of bag filter, 150 ton.


Estonia

Helme
2012
Erection of boiler, prefabrication and erection of piping - 230 ton


Austria

Linz
2020
Assembly of 2 pcs of electrostatic precipitators 400 tons at the Smurfit Kappa plant



Bruck an der Mur
2021
Delivery and erection of CS, SS and ES piping at the Norske Skog plant







- References
- Mission
- Authorities
- Certificates
- Career
ELSTAL AB
Gribbylundsv. 15
187 62 Täby, Sweden
tel. +46 8 6300493
fax. +46 8 6300453
E-mail contact form
Copyright 2000-2012 Elstal AB
Do not use without permission